Database: NSTXU_ECPs.fp7
Records: 62
ECP No.Impacted WBS ElementsControl AccountsECP TitleApproval DateChange LevelContingency Draw KContingency Draw Cum KCBB KContingency Remaining KECP Status
11.7 7700Combine CA 770 and 7710 into one CA (7710) Direct Allocations4/25/20113 Project Manager$77317$16992Approved
21.66100Move the baseline start date for task 6100-0041 to 12 April 20126/8/20113 Project Manager$77317$16992Approved
31.6 6100Reduce man-hours on task 6100-001. Add this budget as M&S on task 6100-0049D.9/10/20113 Project Manager$77317$16992Approved
41.1 1.2 1.8 1304 8200 8210 2420 24901- CA 1304 change to TF procurement (cost/schedule) 2- CA 8200 re-structured and split into two CA's (8200/8210) 3- Remove four tasks from NB Source CA 2420 4- Task accelaration11/10/20112 Federal Project Director$963$963$78280$16029Approved
51.55501 5200 5000Update the Work Breakdown Structure/Dictionary in the Project Execution Plan to ensure that a single Control Account does not occur at more than one WBS element10/6/20113 Project Manager$963$78280$16029Approved
61.7 1.87100 8200 8250Various changes to Control Accounts 7100 (move labor), 8200/8250 (delete WPs and convert to PPs)11/21/20113 Project Manager-$3$960$78277$16032Approved
71.5 5000 Convert task 531-005 held in Planning Package to discrete tasks11/30/20113 Project Manager$960$78277$16032Approved
81.8 8200 8210 Move budget/task (8200-0017A) for purchase of two welding machines from oversight job (8210) to field work job (8200). Change EVT to % Complete.12/2/20113 Project Manager$960$78277$16032Approved
91.3 3300 Control Account 3300: Convert WP 3300-125 EVT from Planning Package to % complete.12/13/20113 Project Manager$960$78277$16032Approved
101.5 5000Convert EVT for activity 531-013 to % complete1/13/20123 Project Manager$960$78277$16032Approved
111.1 1002Control Account 1002. Add scope (cost/schedule) as shown on attached WAF to support reinforcement of passive plates. Change CA 1002 CAM to Neway Atnafu.1/23/20122 Federal Project Director$178$1138$78455$15854Approved
121.1 1.2 1304 1305 2480Delete several unnecessary activities from CA 1304 Inner TF Bundle. Add several activities (cost/schedule) to CA 1305 to accomodate sandblast and prime of OH conductor. Reduce budget on task 2480-0057.2/7/20122 Federal Project Director-$11$1127$78444$15865Approved
131.8 8200 8210 Move task 8200-0017 from Control Account 8210 to Control Account 8200.12/19/20113 Project Manager$1127$78444$15865Approved
141.2 2485 Change the EVT for task 2485-0044A to C (% complete)1/9/20123 Project Manager$1127$78444$15865Approved
151.1 1305Add activities (cost/schedule) to accomplish Aquapour test recommended at FDR2/22/20122 Federal Project Director$31$1158$78475$15834Approved
161.2 2300Engineering and Analysis work to support adding compliance to the HHFW antennas. New CAM = Bob Ellis2 Federal Project Director$1158$78475$15834OPS Scope
171.2 2425Neway Atnafu will replace Martin Denault as the Control Account Manager for Control Account 2425 BL Relocation.1/24/20123 Project Manager$1158$78475$15834Approved
181.2 2450 Resource change for several activities in Control Account 2450, and a change to the start dates for several LOE tasks.1/26/20123 Project Manager-$10$1148$78465$15844Approved
191.1 1.8 1301 8200 Move tasks for drilling additional holes in outer TF flags (tasks 1301-0300 and 1301-0310) from Control Account 1301 to Control Account 82002/21/20123 Project Manager$1148$78465$15844Approved
201.2 2425 Change the start and finish dates for the three LOE tasks.2/21/20123 Project Manager-$6$1142$78459$15850Approved
211.2 2425Replanning of work scope in Control Account 2425 to better fit project timing. Should equate to a slight budget reduction.3/12/20123 Project Manager-$51$1091$78408$15901Approved
221.5 5200Re-planning of Control Account 5200 for Digital Coil Protection5/1/20122 Federal Project Director$27$1118$78435$15874Approved
231.2 2440Transfer responsibility of Control Account Manager (CAM) from Martin Denault to Mark Cropper for Control Account 2440 2nd NBI Beamline2/24/20123 Project Manager$1118$78435$15874Approved
241.1 1307Replace task 1307-2030 Fabricate CS Casing with five (5) new tasks consistent with contract award3/28/20122 Federal Project Director$409$1527$78844$15465Approved
251.2 1.8 2475 8200In Control Account 2475 add steps to the schedule for EPICS timing and Control Interface. In Control Account 8200: Delete task 8200-0102C4/2/20122 Federal Project Director$122$1649$78966$15343Approved
261.1 1.7 1.8 1001 7100 8250Change M&S budget on tasks 1001-0066 and 1001-0066F in Control Account 1001. Also this ECP increases FY2012 resources for Control Account 7100 (Project Management & Integration).Delete redundant tasks from Control Acct. 8250. 3/21/20122 Federal Project Director$210$1859$79176$15133Approved
271.1 1.8 5000 1302 1304 1305 1307 8200Update (replanning) of Control Accounts 1302, 1304, 1305, 1307 including additional tasks and updated resources. Delete Planning Package 8200-PP01A; work not required.5/1/20122 Federal Project Director$22$1881$79198$15111Approved
281.7 7300In Control Account 7300 - Delete task 7300-13 Support of OPA Review3/27/20123 Project Manager-$86$1795$79112$15197Approved
29Milestone PEPIn PEP: Re-define Level II milestone change ref "Friction stir weld coil leads..." In Project Schedule: Re-define activity 1070 to read:RECEIVE FIRST DELIVERY MACHINED INNER TF CONDUCTOR - 30 JUN 20124/3/20122 Federal Project Director$1795$79112$15197Approved
301.7 7300In Control Account 7300 (NB2 Management) delete activity 7300-22.5/2/20122 Federal Project Director-$86$1709$79026$15283Approved
311.2 1.1 2490 1002 2440CA: 1002 Add drafting support CA: 2440 Delete tasks for exit spool piece CA: 2490 Add drafting support and tasks for locating TMP rack on 119' platform5/23/20122 Federal Project Director-$165$1544$78861$15448Approved
32 Not used$1544$78861$15448
331.1 1.7 1000 7710In Control Account 1000 increase the Title III Analysis Support task (LOE) to 900 man hours/FY. This equates to 75 hrs/mo from June 2012 through September 2014. Reduce FY12 and FY13 HP Allocation task in Control Account 7710.6/14/20122 Federal Project Director$258$1803$79120$15189Approved
341.1 1304Change the EVT for several tasks in CA 1304 from 0-100 to % complete. The thought was that milestone payments would be made; however, accruals have been taken based on completion of work and we want to ensure we earn the appropriate value. 6/8/20123 Project Manager$1803$79120$15189Approved
351.1 1305In Control Account 1305 task 1304-1510 had baseline dates of 2Oct12 through 19Sept13. With the early start of fabrication this task requires date changes to Start: 1May2012 through Finish: 31Aug2012.6/21/20122 Federal Project Director-$2$1801$79118$15191Approved
361.1 1304In Control Account 1304 Subcontract S011001 was amended to have Major Tool straighten some of the conductors. This task added an additional $66,260.00 to the contract. This change will add this additional cost in task 1304-1000.6/21/20122 Federal Project Director$66$1867$79184$15125Approved
371.1 1001 Protective measures for the PF-1C coil canister.7/20/20122 Federal Project Director$464$2332$79649$14660Approved
38 Not Used3 Project Manager$2332$79649$14660Not yet submitted for Approval
391.1 1300 1301 1305 4100Additional budget to jobs in CA's 1300, 1301 and 1305. Resources are needed for these tasks that were not previously budgeted.6/26/20122 Federal Project Director$689$3021$80338$13971Approved
401.4 6100 Physics (Stefan) identified new workscope for Diagnostics. This ECP represents the portion of that which Central I&C can service.$3021$80338$13971OPS Scope
411.5 5000PF1 feed changes2 Federal Project Director$3021$80338$13971OPS Scope
421.8 8210Reschedule and re-budget task 8200-0012D "Reinstallation Oversight".7/3/20122 Federal Project Director$159$3180$80497$13812Approved
431.8 1.2 8200 2490Additional tasks for Control Accounts 8200 and 2490. Delete 3 tasks from CA 2490.7/30/20122 Federal Project Director$178$3358$80675$13634Approved
441.2 2425 The HVAC duct over the door between the TFTR and NSTX Test Cells was removed to allow the move of the second neutral beam into the NTC. When this duct is permanently re-installed it should be mounted higher on the wall so it will not interfere with future use of this doorway.7/16/20122 Federal Project Director$20$3378$80695$13614Not yet submitted for Approval
451.1 1300 1301 1302 1304 1305 1306 1307Re-estimating of remaining Center Stack Work8/15/20122 Federal Project Director$1466$4844$82161$12148Approved
461.1 1001Delete tasks 1001-0078 and 1001-0082 in Control Account 1001. These two tasks are redundant.7/24/20122 Federal Project Director-$43$4802$82119$12190Approved
471.1 1.2 1.3 2450 2480 3200Change Control Account Manager (CAM) for several jobs: 2450: from Denault to Neway Atnafu 2480: from Denault to Bill Blanchard 3200: from Denault to Neway Atnafu 8/8/20123 Project Manager$4802$82119$12190Approved
481.1 1200 Updated estimated costs are more than original budget for several tasks. Request additional budget.8/20/20122 Federal Project Director$169$4971$82288$12021Approved
491.5 5501 1200Additional scope (cost/schedule) for Control Account 5501 analysis tasks and additional oversight/documentation time for Control Account 120010/5/20122 Federal Project Director$497$5468$82785$11524Pending
501.6 6100 Add additional budget to oversight task 6100-00009/4/20122 Federal Project Director$38$5506$82823$11486Approved
511.1 1305Add activity 1305-0003 to re-design and manufacture flanges for the TF Quadrant Mold that will allow for complete closure and sealing of the mold7/19/20122 Federal Project Director$10$5516$82833$11476Approved
521.2 2480Convert Planning Package 2480-0076 to discrete activities8/28/20123 Project Manager$5516$82833$11476Approved
531.2 2440Delete tasks 2440-0014 and 2440-0024 from Control Account 24409/19/20122 Federal Project Director-$125$5391$82708$11601Approved
541.2 2490Delete tasks 24910470 and 24910480 from Control Account 24909/24/20122 Federal Project Director-$36$5355$82672$11637Approved
551.4 4500Add scope for analysis/design/fabrication/installation of tFIDA12/4/20122 Federal Project Director$192$5547$82864$11445Approved
561.2 2440 2475 Delete unnecessary task from Control Account 2440. In Control Account 2475 add steps to the schedule for LCC & Low Voltage Power Supply refurbishment. In Control Account 2475 add steps to the schedule for Display Software up-grade.10/19/20122 Federal Project Director$59$5606$82923$11386Approved
571.8 8200Install 6 small ports on NSTX Vacuum Vessel12/4/20122 Federal Project Director$94$5700$83017$11292Approved
581.2 1.1 2460 1001For Control Account 1001 the contract for the machining for Batch 1 of the PFCs came in under budget by ~$90K. For Control Account 2460 there is an increase in job scope12/4/20122 Federal Project Director-$32$5668$82985$11324Approved
591.1 1001 Move BL start date for task 1001-0066F to 12/3/2012 while task is being re-planned.11/12/20123 Project Manager$5668$82985$11324Approved
601.2 2450 $5668$82985$11324
611.1 1305Add task to cover additional work on TF quadrant mold. Change BL dates on two other tasks.2 Federal Project Director$5668$82985$11324
621.1 8200 8210Add re-work of parts received from other WBS elements2 Federal Project Director$5668$82985$11324
FileMaker Pro Version: Pro 11.0v3
Build: 01-25-2011